Project Details at a Glance

What’s happening?
The construction of a new, multi-level, parking garage

Where?
430 and 460 Forest Road, Uptown Sedona

When will it be complete?
Early 2026

Stay connected!

Project Hotline: (928) 852-4164

Email: info@uptownsedonagarage.com

How does this project affect me?

  • This work will require the closure of the public parking area on Forest Road, and routine closure of a small portion along Forest Road in front of the Parking Garage site to all vehicular traffic. Residents in the area should be aware of construction equipment, lane restrictions, reduced speeds, rough road conditions and loud noise. Crews will work with residents to maintain access throughout construction operations. Once complete, Sedona residents are welcome to use the new parking garage to visit Uptown or access the Sedona Shuttle!

  • While this work will have no effect on access to businesses, this work will require the closure of the public parking area on Forest Road, and routine closure of a small portion along Forest Road in front of the Parking Garage site to all vehicular traffic. Once complete, employees and patrons are welcome to use the new parking garage to visit your business!

  • Thanks for visiting Sedona! We are glad you are here. Please note, this work will require the closure of the public parking area on Forest Road, and routine closure of a small portion along Forest Road in front of the Parking Garage site to all vehicular traffic. Once complete, visitors are welcome to use the new parking garage to visit Uptown or access the Sedona Shuttle!

    In the meantime, check out ScenicSedona.com to learn more about our City and plan your stay!

Construction

Timeline

2024

August-November | Excavation and controlled rock blasting

December | Construction of the parking garage anticipated to begin

2026

Early 2026 | Estimated completion